| status = O

| status = O

| construction_began =

| construction_began = 2019

| commissioned =

| commissioned = August 2020

| cost = A$500m

| cost = A$500m

| owner = BEI

| owner = Bright Energy Investments

| operator =

| operator = [[Vestas]]

| employees =

| employees = 6

| wind_farm_type = Onshore

| wind_farm_type = Onshore

| wind_hub_height = {{convert|84|m|ft|0}}

| wind_hub_height = {{convert|84|m|ft|0}}

Line 26: Line 26:

}}

}}



'''Warradarge Wind Farm''' is located {{convert|15|km}} northeast of [[Warradarge, Western Australia|Warradarge]], and {{convert|30|km}} southeast of [[Eneabba, Western Australia|Eneabba]] in the [[Mid West (Western Australia)|Mid West]] region of [[Western Australia]]. Construction commenced in 2019 and the first of its planned 51 turbines was completed on 21 January 2020. The wind farm has been operational since then.<ref>{{cite news |url=https://reneweconomy.com.au/first-turbine-up-at-180mw-warradarge-wind-farm-in-w-a-87556/ |access-date=21 January 2020 |title=First turbine up at 180MW Warradarge Wind Farm in W.A. |first=Sophie |last=Vorrath |date=21 January 2020 |newspaper=Renew Economy}}</ref>

'''Warradarge Wind Farm''' is located {{convert|15|km}} northeast of [[Warradarge, Western Australia|Warradarge]], and {{convert|30|km}} southeast of [[Eneabba, Western Australia|Eneabba]] in the [[Mid West (Western Australia)|Mid West]] region of [[Western Australia]]. Construction commenced in 2019 and the first of its planned 51 turbines was completed on 21 January 2020. The wind farm has been operational since August 2020.<ref name="startup">{{cite web |title=Warradarge Wind Farm powers up |url=https://static1.squarespace.com/static/5d84816baf58642d05f43678/t/5f33887f3f416d67e270af71/1597212804076/BEI+MEDIA+RELEASE-+Warradarge+first+generation+12Aug20.pdf|publisher=Bright Energy Investments |date=12 August 2020 |access-date=30 July 2024 |location=Perth, WA |date=12 August 2020}}</ref><ref>{{cite news |url=https://reneweconomy.com.au/first-turbine-up-at-180mw-warradarge-wind-farm-in-w-a-87556/ |access-date=21 January 2020 |title=First turbine up at 180MW Warradarge Wind Farm in W.A. |first=Sophie |last=Vorrath |date=21 January 2020 |newspaper=Renew Economy}}</ref>



It is owned by [[Bright Energy Investments]], a joint venture between the Dutch fund manager DIF Capital Partners (40.05%), Australian industry superannuation fund [[Cbus (superannuation fund)|Cbus]] (40.05%), and the Western Australian government's electricity generator and retailer [[Synergy (electricity corporation)|Synergy]] (19.9%). The construction and maintenance contracts are with Danish company [[Vestas]].<ref>{{cite web |title=Application Summary - The Warradarge Wind Farm |url=http://www.erawa.com.au/cproot/20180/2/Application%20Summary%20-%20For%20Public%20Release%20-%20V2%20-%20BEI%20WWF%20Pty%20Ltd%20as%20Trustee%20for%20the%20WWF%20Trust.pdf |publisher=Bright Energy Investments |access-date=11 February 2020 |date=2018}}</ref><ref name=renew>{{cite news |last1=Parkinson |first1=Giles |title=Cbus, DIF join Synergy to boost wind and solar portfolio |url=https://reneweconomy.com.au/cbus-dif-join-synergy-boost-wind-solar-portfolio-94378/ |access-date=11 February 2020 |work=Renew Economy |date=11 April 2018 |location=Mullumbimby, NSW}}</ref>

It is owned by [[Bright Energy Investments]], a joint venture between the Dutch fund manager DIF Capital Partners (40.05%), Australian industry superannuation fund [[Cbus (superannuation fund)|Cbus]] (40.05%), and the Western Australian government's electricity generator and retailer [[Synergy (electricity corporation)|Synergy]] (19.9%). The construction and maintenance contracts are with Danish company [[Vestas]].<ref>{{cite web |title=Application Summary - The Warradarge Wind Farm |url=http://www.erawa.com.au/cproot/20180/2/Application%20Summary%20-%20For%20Public%20Release%20-%20V2%20-%20BEI%20WWF%20Pty%20Ltd%20as%20Trustee%20for%20the%20WWF%20Trust.pdf |publisher=Bright Energy Investments |access-date=11 February 2020 |date=2018}}</ref><ref name=renew>{{cite news |last1=Parkinson |first1=Giles |title=Cbus, DIF join Synergy to boost wind and solar portfolio |url=https://reneweconomy.com.au/cbus-dif-join-synergy-boost-wind-solar-portfolio-94378/ |access-date=11 February 2020 |work=Renew Economy |date=11 April 2018 |location=Mullumbimby, NSW}}</ref>



Originally proposed in 2012 for up to 100 turbines generating 250 MW of electricity, when completed the wind farm will generate up to 180 MW from 51 turbines for the [[South West Interconnected System]], the [[electricity grid]] in southern Western Australia.<ref name=renew/><ref>{{cite web |title=Warradarge Wind Farm |url=http://www.epa.wa.gov.au/proposals/warradarge-wind-farm |website=Western Australian Environmental Protection Authority |access-date=11 February 2020 |location=Joondalup, WA |date=18 October 2012}}</ref> This is equivalent to providing power for the typical [https://www.climateaction.wa.gov.au/initiatives/warradarge-wind-farm annual electricity consumption of 144,000 homes in Western Australia].

Originally proposed in 2012 for up to 100 turbines generating 250 MW of electricity, the wind farm was completed in 2020 with 51 turbines, capable of generating up to 180 MW for the [[South West Interconnected System]], the [[electricity grid]] in southern Western Australia, equivalent to providing power for 144,000 homes.<ref name=renew/><ref>{{cite web |title=Warradarge Wind Farm |url=http://www.epa.wa.gov.au/proposals/warradarge-wind-farm |website=Western Australian Environmental Protection Authority |access-date=11 February 2020 |location=Joondalup, WA |date=18 October 2012}}</ref><ref name=bright>{{cite web |title=Warradarge Wind Farm |url=https://www.brightenergyinvestments.com.au/warradarge-wind-farm-1 |publisher=Bright Energy Investments |access-date=30 July 2024 |location=Perth, WA}}</ref>



The wind turbines are manufactured by Vestas with 66 metre blades and a tip height of 152 metres above the ground. [[Western Power (networks corporation)|Western Power]] will construct a new {{convert|10|km}} transmission line from the wind farm to the existing 330 kV transmission network.<ref name="BEI">{{cite web |url=https://www.brightenergyinvestments.com.au/warradarge-wind-farm-1 |publisher=[[Bright Energy Investments]] |title=Warradarge Wind Farm - Under Construction |access-date=21 January 2020}}</ref>

The wind turbines are manufactured by Vestas with 66 metre blades and a tip height of 152 metres above the ground. [[Western Power (networks corporation)|Western Power]] constructed a {{convert|10|km}} transmission line from the wind farm to the existing 330 kV transmission network near Eneabba.<ref name="BEI">{{cite web |url=https://www.brightenergyinvestments.com.au/warradarge-wind-farm-1 |publisher=[[Bright Energy Investments]] |title=Warradarge Wind Farm - Under Construction |access-date=21 January 2020}}</ref><ref name=bright/>



Funding was announced for a [https://www.wa.gov.au/government/media-statements/McGowan-Labor-Government/%243-billion-investment-for-a-cleaner-energy-future-20230511 potential expansion of the wind farm] in 2023.

In 2023 funding was announced for a potential expansion of the wind farm.<ref>{{cite web |title=$3 billion investment for a cleaner energy future |url=https://www.wa.gov.au/government/media-statements/McGowan-Labor-Government/%243-billion-investment-for-a-cleaner-energy-future-20230511 |publisher=Government of Western Australia |access-date=30 July 2024 |location=Perth WA |date=11 May 2023}}</ref>



== Operations ==

== Operations ==

AEMO records begin in August 2020 for the wind farm. The generation table uses [https://aemo.com.au/energy-systems/electricity/wholesale-electricity-market-wem/data-wem/market-data-wa AEMO Facility SCADA] to obtain generation values for each month. Warradarge's code is WARRADARGE_WF1. A SUMIF operation is used on the data published by AEMO to get the total (shown in the table below). Note that each month's values start 8 hours into the respective month and extend 8 hours into the next month, in line with the trading day defined in the Wholesale Energy Market Rules.<ref>{{cite web | url=https://www.wa.gov.au/government/document-collections/wholesale-electricity-market-rules | title=Wholesale Electricity Market Rules }}</ref><syntaxhighlight lang="c">

Operations began in August 2020.<ref name="startup"/> The generation table uses [https://aemo.com.au/energy-systems/electricity/wholesale-electricity-market-wem/data-wem/market-data-wa AEMO Facility SCADA] to obtain generation values for each month. Warradarge's code is WARRADARGE_WF1. A SUMIF operation is used on the data published by AEMO to get the total (shown in the table below). Each month's values start 8 hours into the respective month and extend 8 hours into the next month, in line with the trading day defined in the Wholesale Energy Market Rules.<ref>{{cite web | url=https://www.wa.gov.au/government/document-collections/wholesale-electricity-market-rules | title=Wholesale Electricity Market Rules }}</ref><syntaxhighlight lang="c">


=SUMIF(E2:E Last Row,"*WARRADARGE_WF1*",F2:F Last Row)

</syntaxhighlight>

</syntaxhighlight>

{| class="wikitable"

{| class="wikitable"

Line 87: Line 87:

|66,141

|66,141

|}

|}

Note: Asterisk indicates power output was limited during the month.



==References==

==References==


Revision as of 06:03, 30 July 2024

Warradarge Wind Farm
Map
CountryAustralia
LocationWarradarge
Coordinates29°58′48″S 115°29′24″E / 29.98000°S 115.49000°E
StatusOperational
Construction began2019
Commission dateAugust 2020
Construction costA$500m
Owner(s)Bright Energy Investments
Operator(s)Vestas
Employees6
Wind farm
TypeOnshore
Hub height84 metres (276 ft)
Rotor diameter136 metres (446 ft)
Power generation
Units operational51 × 3.6 MW
Make and modelVestas V136
Units under const.51 × 3.6 MW
Nameplate capacity183.6 MW
Capacity factor38%
External links
Websitewww.brightenergyinvestments.com.au/warradarge-wind-farm-1

Warradarge Wind Farm is located 15 kilometres (9.3 mi) northeast of Warradarge, and 30 kilometres (19 mi) southeast of Eneabba in the Mid West region of Western Australia. Construction commenced in 2019 and the first of its planned 51 turbines was completed on 21 January 2020. The wind farm has been operational since August 2020.[1][2]

It is owned by Bright Energy Investments, a joint venture between the Dutch fund manager DIF Capital Partners (40.05%), Australian industry superannuation fund Cbus (40.05%), and the Western Australian government's electricity generator and retailer Synergy (19.9%). The construction and maintenance contracts are with Danish company Vestas.[3][4]

Originally proposed in 2012 for up to 100 turbines generating 250 MW of electricity, the wind farm was completed in 2020 with 51 turbines, capable of generating up to 180 MW for the South West Interconnected System, the electricity grid in southern Western Australia, equivalent to providing power for 144,000 homes.[4][5][6]

The wind turbines are manufactured by Vestas with 66 metre blades and a tip height of 152 metres above the ground. Western Power constructed a 10 kilometres (6.2 mi) transmission line from the wind farm to the existing 330 kV transmission network near Eneabba.[7][6]

In 2023 funding was announced for a potential expansion of the wind farm.[8]

Operations

Operations began in August 2020.[1] The generation table uses AEMO Facility SCADA to obtain generation values for each month. Warradarge's code is WARRADARGE_WF1. A SUMIF operation is used on the data published by AEMO to get the total (shown in the table below). Each month's values start 8 hours into the respective month and extend 8 hours into the next month, in line with the trading day defined in the Wholesale Energy Market Rules.[9]

Warradarge Wind Farm Generation (MWh)
Year Total Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2020 197,134 N/A N/A N/A N/A N/A N/A N/A 7,131 31,244 37,146 54,546 67,067
2021 604,089 63,260 68,094 55,782 23,891 45,563 44,096 51,823 45,202 45,636 46,432 48,168 66,141

References

  1. ^ a b "Warradarge Wind Farm powers up" (PDF). Perth, WA: Bright Energy Investments. 12 August 2020. Retrieved 30 July 2024.
  2. ^ Vorrath, Sophie (21 January 2020). "First turbine up at 180MW Warradarge Wind Farm in W.A." Renew Economy. Retrieved 21 January 2020.
  3. ^ "Application Summary - The Warradarge Wind Farm" (PDF). Bright Energy Investments. 2018. Retrieved 11 February 2020.
  4. ^ a b Parkinson, Giles (11 April 2018). "Cbus, DIF join Synergy to boost wind and solar portfolio". Renew Economy. Mullumbimby, NSW. Retrieved 11 February 2020.
  5. ^ "Warradarge Wind Farm". Western Australian Environmental Protection Authority. Joondalup, WA. 18 October 2012. Retrieved 11 February 2020.
  6. ^ a b "Warradarge Wind Farm". Perth, WA: Bright Energy Investments. Retrieved 30 July 2024.
  7. ^ "Warradarge Wind Farm - Under Construction". Bright Energy Investments. Retrieved 21 January 2020.
  8. ^ "$3 billion investment for a cleaner energy future". Perth WA: Government of Western Australia. 11 May 2023. Retrieved 30 July 2024.
  9. ^ "Wholesale Electricity Market Rules".